Multi-band Offers

A unit offers 30 MW at 80 NIS, then 30 MW at 150 NIS. Bands interleave across units in price order. The marginal band sets the MCP.

Generation Units Table
Pre-optimization unit parameters
Unit Fuel Technology Capacity(MW) Min Load(MW) Ramp(MW/min) Spin Res(MW) Freq Res(MW) Price(NIS/MWh)
GAS_1 GAS CCGT 80 20 1.67 0 0 80-150
GAS_2 GAS CCGT 60 20 1.67 0 0 120
GAS_3 GAS SIMPLE_CYCLE 50 15 1.67 0 0 200
System Parameters
Time Horizon 1 intervals (0.5h)
Interval Duration 30 minutes
Spinning Reserve (Up) 0 MW
Spinning Reserve (Down) 0 MW
Frequency Reserve 0 MW
Value of Lost Load 100000 NIS/MWh
Coal Priority Dispatched Last
Demand
Total Demand 130 MW